FTP Server

🚧

At the moment, configurations described in this article are proprietary for one of our clients

Activate FTP server connection

  • Navigate to Organizations > Organization List tab
  • Click on Edit icon of the top organization - The Manufacturer
1920
  • On the Organization Information screen, click on Use FTP check box
  • Click Save to confirm the change
1920

Pull orders from FTP server to second level branches

  • Login with the administrator account of each branch
  • Navigate to Orders > Sales Orders tab
  • Click on icon on the toolbar
  • On the Sync from ERP form, click on Branch field, select the appropriate branch from the drop down menu
798
  • Next, input data into IP/Domain; Port; Username and Password fields
  • Click on ERP/DMS Date field, select the date the orders have been created on the FTP server from the drop down calendar. Then, click on Delivery Date (vRoute) field, select a date to execute these orders from the drop down calendar
  • Click on Pull. The system will start pulling orders of all depot under the selected branch from FTP server to Abivin vRoute
1911

Optimize routes for orders of second level branches

  • After you have pulled the orders for the second level branches from FTP server to Abivin vRoute, you can proceed to optimize routes for those orders
1920
  • After you have optimized routes, as you click on Lock Route, the Push Data to ERP form will appear. Input the FTP server information into the fields IP or Domain; Port; Username; Password, then click Push to push the route data to FTP server
1920

Consolidate optimized orders of second level branches

  • After you have optimized and locked routes for the orders of all second level branches as described above, you can now consolidate those orders into one big order and pull to the first level distributor

Enable Order Consolidation configuration

  • Navigate to Organizations > Organization List tab
  • Click on Edit icon of the Distributor that you want to set as the first level distributor
1920
  • On the Organization Information screen, click on Order Consolidation check box
  • Click Save to confirm the change
1920

Setup Branch as Customer

  • In order for the first level distributor to be able to pull data from the second level branches, you have to create customers whose Customer Code attributes are the same as Organization Code attributes of those branches. They will be under direct management of the first level depot

❗️

We currently support only nine branches

1887

Setup first level Depot

  • You have to create a first level depot under the direct management of the first level distributor. This depot will store products that will later be delivered to the second level branches
1920

Consolidate optimized orders of second level branches

  • Navigate to Orders > Sales Orders tab
  • Click on icon on the toolbar
  • On Sync from ERP form, click on the Branch field, input the Organization Name of the First Level Distributor into the search bar, then select from the drop down menu
1920
  • The Sync from ERP form will change to Fetch orders from Branches form
  • Next, click on the icon under Delivery Date (vRoute) text. On the drop down calendar, you need to select the date on which the orders have been optimized and locked
  • Next, click on the icon under ERP/DMS Date text. On the drop down calendar, you need to select the date on which the orders have been created on the FTP server
  • Finally, click on Pull to begin consolidating orders from the second level branches into one big order and pull to the first level depot

📘

Even the missing orders - orders of the second level branches that were unable to be optimized, will also be consolidated into the big order pulled to the first level depot. This is to ensure that the first level depot supplies enough products for the second level branches

Optimize routes for first level depot

  • After the orders from second level branches have been consolidated and pulled to the first level depot, you can proceed to optimize routes for these orders
  • Note: During the optimization process, you have to select the First level Distributor to optimize routes, instead of branches like usual
1920

Choose the first level Distributor

  • After you have optimized routes, as you click on Lock Route, the Push Data to ERP form will appear. Input the FTP server information into the fields IP or Domain; Port; Username; Password, then click Push to push the route data to FTP server

Rules when allocating orders

  • The orders are allocated based on Volume attribute. If the volume of a big order exceeds the volume capacity of every available vehicles of the first level depot, it will automatically be split into smaller orders. The volume attribute of the split orders will be based on the volume capacity of the available vehicles, starting from the vehicle with the largest volume capacity
  • One vehicle of the first level depot can deliver orders of multiple second level depot vehicles. On the other hand, orders of one vehicle of a second level depot can only be delivered by one single vehicle of the first level depot